Dangote Refinery still in its pre-commissioning phase, yet to be full licence, says NMDPRA

Dangote Refinery 2

The Nigerian Midstream and Downstream Petroleum Regulatory Authority (NMDPRA) has revealed that Dangote Refinery is still in its pre-commissioning phase and has yet to receive a full operational licence.

This is coming at a time Danote Refinery and Nigerian National Petroleum Company Limited (NNPCL) contending Premium Motor Spirit (PMS) or petrol price

The update comes amid high expectations for the Dangote Refinery, which is anticipated to significantly reduce Nigeria’s reliance on fuel imports once it achieves full operational status.

The Head of Public Affairs at NMDPRA, George Ene-Ita, clarified that the refinery is currently undergoing a phased process, with only two out of four priority sections approved for the introduction of hydrocarbons.

“The entire plant is subdivided into four sections technically referred to as priorities one, two, three, and four,” Ene-Ita explained, adding that “At this stage of pre-commissioning, only priorities one and two have been given approval to introduce hydrocarbons, which allows the plant to operate on a test-run basis.”

Under this condition, Ene-Ita said the refinery is permitted to produce petroleum products such as diesel, jet fuel, and kerosene, which are then released into the market under regulatory supervision.

This pre-commissioning phase also involves conducting rigorous pre-startup and safety audits of the facility, Ene-Ita told The Guardian.

See also  My family is now homeless - Man whose ‘N300m’ house was demolished in Lagos says

He noted that the audits include tests on the plant’s mechanical, electrical, and instrumentation systems to ensure the refinery’s readiness for full-scale production. Ene-Ita said full production and an increased volume of PMS would only be achieved when approval is given to introduce hydrocarbons into priorities three and four.

“Once these sections are operational, the plant will undergo a 90-day observation period during which additional tests and audits will be carried out to confirm compliance with regulatory guidelines. If, after 90 days, our technical team confirms that the facility adheres to all parameters, the refinery will be issued a License to Operate (LTO).

Recommended For You

About the Author: Akelicious

Leave a Reply

Your email address will not be published. Required fields are marked *