Again, NNPC Fails to Meet Port Harcourt Refinery Deadline

NNPC

NNPC has again failed to begin fuel production at the Port Harcourt refinery after the seven postponement

This is despite the refinery failing to commence operations after about six postponements as of August 2024.

Many promises made to Nigerians by the Federal Ministry of Petroleum Resources and NNPC about the refinery have continued to hit brick walls.

After the failure of the early August promise, the Chief Financial Officer of the NNPC, Umar Ajiya, said the Port Harcourt refinery will commence operations in September 2024.

Speaking to journalists in August, Ajiya had said petroleum products would be ready for testing before being supplied to the domestic market in September.

As September ended yesterday, the NNPC did not give an update about the refinery.

Our correspondent contacted the NNPC last week for an update about the refinery, but there was no response.

The Chief Corporate Communications Officer of the oil firm, Olufemi Soneye, did not reply to enquiries sent to him on September 22 and 30, 2024.

However, Maire Tecnimont SpA, the contractor overseeing the rehabilitation of the Port Harcourt refinery, said it would provide details on the project’s completion by or before October 2.

The contractor conveyed this through a law firm, Olajide Oyewole LLP, in response to a letter from a Senior Advocate of Nigeria, Femi Falana, who had inquired about the completion timeline for the refinery’s rehabilitation.

See also  Yahaya Bello Leaves EFCC Office Without Interrogation

In reply to Falana’s request, the law firm stated that its client received his letters dated September 17 and 24 regarding the contract with the NNPC and is considering the inquiries.

“Our client is considering your letters, and they intend to get back to you on or before 2 October 2024,” the law firm had said.

Since December 2023, NNPC, which is in charge of all the government refineries, has given Nigerians different dates, assuring them that the refinery would begin the sale of refined products soon.

In July, the Group Chief Executive Officer of the NNPC, Mele Kyari, stated categorically that the refinery would come into operation in early August.

Recommended For You

About the Author: Akelicious

Leave a Reply

Your email address will not be published. Required fields are marked *